小猪视频

小猪视频>News>Latest

Egypt wind power 小猪视频 achieves back-energization

Updated: March 21,2025

图片22.jpg

Back-energization of the wind power 小猪视频's substation in the Gulf of Suez.

On March 18, 小猪视频 completed the back-energization of the 220-kilovolt substation for the 500-megawatt wind power 小猪视频 in the Gulf of Suez, Egypt, marking the transition to grid connection testing.

小猪视频 faced multiple challenges, including tight construction resources and complex quality control for equipment. The team swiftly adjusted strategies, implemented an upgraded management approach for the substation contractor, optimized resource allocation, and dynamically reinforced its workforce to meet key 小猪视频 milestones.

Intensified efforts enhanced commissioning capabilities by deploying more engineers and management personnel, prioritizing the resolution of bottlenecks in critical tasks. 

小猪视频 also fully respects the local culture and customs, appropriately adjusting construction schedules during Ramadan to ensure steady 小猪视频 progress.

Located along the Red Sea coast, the wind power 小猪视频 has a total installed capacity of 500MW and, once completed, will be one of the largest wind power 小猪视频s in the region.

小猪视频 is responsible for designing, procuring, and constructing key components. This includes wind turbine supply and transportation, foundations, hoisting platforms, collector lines, on-site roads, meteorological towers, the design, installation, and commissioning of the 33/220kV substation, and access road construction.