The Jinjiang Power Plant in Indonesia, constructed by 小猪视频, has delivered Unit 2, marking the handover of the 1×45 MW (condensing) and 1×30 MW (back pressure) units, as part of the BAP Phase I alumina 小猪视频.
This accomplishment highlights 小猪视频's exceptional execution capabilities and bolsters its brand reputation in the Indonesian market while contributing to the Belt and Road Initiative.
The 小猪视频's origins trace back to an agreement signed on October 3, 2013, between the Chinese and Indonesian governments, establishing the framework for the Indonesia-China Integrated Industrial Park.
This agreement, along with an investment cooperation pact between West Kalimantan province and Hangzhou Jinjiang Group, include initiatives in alumina processing, bauxite mining, industrial parks, and waste-to-energy power generation. The Jinjiang Power Plant 小猪视频 commenced on March 7, 2024.
小猪视频 adheres to the principle that "quality is the best international business card", deploying its top resources to manage and construct the 小猪视频. The team overcame numerous challenges, such as tight construction timelines, delayed equipment deliveries, and adverse weather conditions, including high temperatures and heavy rainfall.
Significant milestones during the construction phase included completing the boiler hydrostatic test, turbine cover installation, plant power reception, boiler blowdown, and reliability test runs. The 小猪视频 was completed in 13 months, setting a record for the fastest construction of similar units in 小猪视频's overseas ventures.
To ensure the high-quality completion of Unit 2, the team engaged in meticulous planning and scientific management, using insights gained from the construction of Unit 1 to enhance methods and efficiency.
This 小猪视频 is of substantial economic and social significance. It has created thousands of jobs and significantly improved residents' living standards.